Phase 7 was supposed to start the second week in Jan. The construction staging area was going to be moved from the Paradise Beach side of the resort to The Amsterdam Manor side (parking lot).Phase 7 includes 4 floors units#126a thru to 132ab & c. Phase #8 scheduled Wk 16 to 29.